Water Sector Infrastructure using DPC: Does the CAP fit?
The Haweswater Aqueduct Resilience Programme (“HARP”) project achieving initial financial close and moving to the ‘build’ phase, along with the re-publication in May of Ofwat’s Final Determinations for the 2024 Price Review, has focused attention in the infrastructure community on the market opportunity offered by the ‘Direct Procurement for Customers’ (“DPC”) model.
QMPF has explored the nature and scale of the market and the commercial and financial aspects that participants will need to continue to monitor as opportunities emerge.
DPC Procurement: the basic structure
DPC is a procurement process in which a Competitively Appointed Provider (“CAP”) is selected to design, build, finance, maintain, and operate water sector assets. The CAP is appointed by a regulated water company (the “Appointee”) but finances the asset independently and operates outside the Appointee’s regulatory ringfence. This structure is intended to bring new expertise and capital into the sector, while keeping the regulated company focused on its core operations. Ofwat has provided a diagram to illustrate this structure:

Where is DPC procurement expected to be used?
DPC is expected to be used for capital projects that meet two main criteria: a size threshold, where total lifetime expenditure (“totex”) exceeds £200 million, and a discrete project test, which requires the project to be distinct and separable from the company’s existing network and operations. Ofwat encourages companies to consider combining smaller projects to meet the size threshold. While the previous requirement to compare DPC with in-house delivery has been dropped, companies must still demonstrate value for money throughout the procurement process.
Where does SIPR fit in?
The Specified Infrastructure Project Regulations (SIPR) remain an alternative procurement route, particularly for larger or more complex projects. The delivery of Thames Tideway Tunnel demonstrated the potential of the SIPR delivery route and three PR24 projects have been identified as more appropriate for the SIPR model. The key distinction is that under SIPR, the Infrastructure Provider (“IP”) is directly regulated by Ofwat and holds a distinct license. However, SIPR involves higher setup and regulatory costs, so Ofwat expects most projects to be delivered via DPC, reserving SIPR for cases where direct regulation offers clear advantages. In-house delivery remains possible for a limited number of projects, subject to Ofwat approval.
What can we expect to come to market?
With Ofwat’s updated guidance, a significant number of projects are expected to come to market under the DPC model. HARP serves as an early example, and Ofwat has identified 23 projects in its PR24 Final Determinations that are likely to be procured through DPC. This pipeline represents a substantial opportunity for investors and service providers in the sector:
The pipeline is analysed below:

Source: QMPF analysis, Ofwat PR24 Final Determinations
What tender models are being considered?
Ofwat recognises that different projects may require different approaches to selecting a CAP, referred to as the ‘tender model’. In some cases, the CAP may be appointed early, taking on responsibility for design, surveys, planning, procurement, build, and operation. More commonly, however, the CAP is chosen later, after the Appointee has completed initial design and planning. Ofwat also allows for a ‘split’ model, where separate CAPs are appointed for initial design and for delivery and operation. To date, DPC projects have tended towards later appointment of the CAP, with the Appointee retaining responsibility for initial design, planning, surveys and in some cases both detailed design and initial elements of procurement, with the CAP brought in later. The choice of model has important implications for risk transfer and project delivery and will be shaped by the specific needs and risks of each project.
Financial structure and risk
Ofwat’s guidance on DPC leaves room for negotiation regarding financing risk. It acknowledges that, given the long-term nature of water sector projects and current economic conditions, not all funding and cost risks can be transferred to the CAP. The threshold outturn cost approach is used to manage funding requirement risk, allowing the CAP to benefit from cost savings while providing protection against significant overruns, with some risk ultimately passed to customers. Mechanisms for adjusting payments based on the market cost of debt and sharing refinancing gains are also discussed, drawing on lessons from the Thames Tideway project.
This could result in the CAP retaining the financial benefit where it can deliver the project within the threshold outturn, but has protection, through amendment to the CAP charge payment (and so passing of the risk to customers) where there are significant cost overruns. It is clear this will remain a critical aspect for the market to understand through the procurement process and to document in concluding the CAP Agreement and will be subject to significant due diligence through the fund raising process and funder engagement processes.
Similarly, the mechanisms for ‘market cost of debt’ adjustment will require to be negotiated. Again, Thames Tideway may provide guidance; its financing cost adjustment worked on the basis of protecting the IP for movements in the underlying real cost of debt outside of a cap and collar and with a presumption in relation to the proportion of debt and equity in the project. For Thames Tideway the movement was with reference to a benchmark index. The agreement of the relevant index used, the extent of the cap and collar and establishing the timing of benchmarking will be critical for market participants.
Refinancing risk may be more straight forward. There is an increasingly standardised approach to refinancing gain share that Ofwat anticipates seeing from DPC project: 90% of gains from margin enhancement and 50% of other relevant refinancings, flowing back to customers through a CAP charge reduction.
Other financial considerations include inflation, requirements of debt funders and payment mechanisms reflecting the nature of the asset and provision (e.g. availability only, or with demand components and reflecting the extent of ongoing maintenance/operations relative to capex and how that manifests in both debt structure and CAP payment indexation). The significant asset life anticipated will require consideration of residual value and handback requirements. As DPC projects emerge we also anticipate further attention on what might be the optimal project duration, both reflecting the asset and financing options, to deliver best value.
Other risk allocations
The specific risk allocation is expected to vary by project and will be subject to the negotiated CAP Agreement in order that Appointees have flexibility to achieve best value for customers. However, Ofwat’s guidance to Appointees offers insight into the initial risk allocation that can be anticipated:
| Risk | Ofwat expected allocation |
| Planning, land acquisition and consents | Expected to be borne by the Appointee (or Customers) though early appointment of a CAP could see the CAP acting as agent for the Appointee. Land expected to remain in Appointee ownership and provided to the CAP under licence or lease. |
| Works information | As seems inherently the most appropriate party to bear this, this is assumed to remain with the Appointee. |
| Existing asset interface | The risk that interfaces are poorly defined or mismanaged, and the potential for this to cause delay would remain with the Appointee. |
| Changes in scope | The CAP would not be expected to bear this risk or manage changes arising from regulatory or legal changes in construction. |
| Cost overruns | Expected to be an area of significant commercial negotiation on a project specific basis, Ofwat recognises that these risks will need to be shared between the CAP and Appointee (and likely flow to customers via CAP payment adjustment) to avoid inefficient risk pricing and deliver value for money. |
| Site conditions | Allocated to the CAP but recognising this may not be achievable in all circumstances, without limitation and certainly less deliverable on brownfield land. |
| Detailed design | Expected to be transferred to the CAP to ensure the detailed design meets the project requirements. |
| Third party stakeholder management | To be managed jointly between the CAP and Appointee. |
| Commissioning | Appropriately, and in line with infrastructure sector norms, this would remain the risk of the CAP. |
| Statutory and regulatory obligations in operations | While the Appointee cannot contract out regulatory requirements, we would expect the CAP to be incentivised to meet operational performance requirements and Appointees to focus on both deductions and, ultimately, termination rights in negotiating the CAP Agreement. |
| Operating costs and Operational performance | As is typical in similar public:private infrastructure finances, these are core risk transferred to the CAP. Ofwat recognises that some specific operational delivery (and risk) is likely to remain best managed by the Appointee on specific projects. |
| Operation scope change | Ofwat would expect well established change mechanics from wider infrastructure projects to be adopted to appropriately manage delivery of scope changes, their financing and incorporation in the operational DPC project and CAP payment mechanism. |
| Defects | Ofwat allocates this to both the CAP and Appointee, though we would expect the majority of this risk to be transferred to the CAP, other than for specific circumstances. |
| Demand risk / overutilisation | These are allocated to the Appointee, though we would expect on some projects some demand risk (within the expected upper and lower bounds) may sit with the CAP. It is inherent on the Appointee to scope projects and their design requirements to reflect expected long term demand. |
| Handback risk | Allocated to the CAP, with Appointee requirements clearly determined under the CAP agreement. |
| Customer bad debt | The CAP would not expect to bear exposure to this risk (and funders would likely not accept/price for it), which remains best managed by Appointees. |
| Change in law / regulation | General change in law risk expected to lie with the CAP but DPC specific change in law would remain with the Appointee/customers (through adjustment to the CAP payment), this is in line with standard risk allocation across other UK infrastructure projects. |
What have we learnt from HARP?
HARP, and the work undertaken by United Utilities, Cascade Infrastructure (Strabag-Equitix Consortium) and their advisers, demonstrates the potential for the DPC structure to deliver projects to start of construction, in relatively short timescales.
The commercial positions accepted by each party will likely emerge as the project progresses, but we expect there has been an element of pragmatism to reach this stage and deliver a positive outcome. Should the commercial positions hold water (no pun intended) they may provide a framework for future projects. This is particularly true where those projects may be less complex from a delivery perspective, have lower funding requirements and shorter construction phases.
However, the HARP project is not without uncertainties. The extent to which funding for the full construction programme is secured remains to be confirmed and the financing cost for all stages is expected to only be known as the project moves forwards. How the changes in market funding costs and construction cost changes are shared, and the extent to which they are passed on to water customers, will only be known with time.
The reaction to this outside of the infrastructure sector will matter. It will be of importance to all in the sector, including both CAP partners and the water companies, to provide third parties with clarity on the risk transfer achieved and the value for money the DPC approach offers. This will set the platform for further delivery of critical and much needed infrastructure.
The ability of the DPC structure to move to financial close on complex projects, to share risk appropriately and to recognise that the risks in relation to holding funding costs and construction costs could be shared in a different way, but offer better overall value for money, provides potential lessons across the wider infrastructure sector.
How can QMPF help?
QMPF has over 20 years practical experience supporting private sector and public sector clients delivering infrastructure development under a range of financing structures, from PPP/PFI through LIFT, NPD and hub. We understand the commercial complexities to be negotiated, routes to delivering a robust funding club and the financial modelling that underpins equity, debt and procurer analysis. Our experienced team would be delighted to discuss DPC and wider infrastructure opportunities with you.
Glossary:
| Term | Definition |
| CAP | Competitively Appointed Provider, third party provider for the delivery of major projects under the DPC model. |
| Capex | Capital Expenditure for an identified project. |
| DPC | Direct Procurement for Customers, a water or wastewater company competitively tendering for services in relation to the delivery of certain major projects. |
| Final Determinations | Final decisions that set the price controls and performance targets for water and sewerage companies in England and Wales, including relevant investment decisions. |
| HARP | Haweswater Aqueduct Resilience Programme, the CAP programme for delivery of maintenance of the 110km water pipeline in North West England including the replacement of six tunnel sections along the pipeline route. |
| hub | Scottish infrastructure initiative to deliver public sector construction projects through regional partnerships called hubCos. |
| IP | Infrastructure Provider, a Third party company, designated to finance, build, operate, and maintain large new water infrastructure projects under Ofwat’s regulation appointed via a SIPR procurement process. |
| LIFT | Local Improvement Finance Trust, a public-private partnership model used to finance, build, and maintain primary care facilities through joint ventures between the public and private sectors in the UK. |
| NPD | Non-Profit Distributing, a procurement model in Scotland used for privately financed public infrastructure projects, replacing the old PFI system and seeking to cap private sector partner returns. |
| Ofwat | The Water Services Regulation Authority, responsible for economic regulation of the privatised water and sewerage industry in England and Wales. |
| PPP/PFI | Public Private Partnership / Private Finance Initiative, procurement methods for the delivery, financing, operation and maintenance of public sector infrastructure. |
| PR19 | Ofwat Price Review 2019. |
| PR24 | Ofwat Price Review 2024 is the latest five-year regulatory process that determines the price limits for water companies in England and Wales for 2025-2030. |
| SIPR | Specified Infrastructure Project Regulations, competitively tendered route for the water sector in relation to the design, build, financing, maintenance and operation of certain English major projects that results in the delivery company, or IP, being a separately regulated entity. |
| Totex | Total Expenditure, operational and capital expenditure for an identified project. |
More News…


